It depends on so many different variables. We can’t commit to a timeframe until we have a truly clear idea of the project’s design, architecture, and required permits. It depends upon the scope of the overall job.

For an idea, renovations and or addition:

  • Design phase – takes 2 to 3 months on average  
  • Permit phase – typically takes a month for the city/county to approve  
  • Construction phase – approximately 5 months to 7 months depending on scope of work 

New construction 

  • Design phase – most of our projects take 2 to 4 months to design 
  • Permits phase – 1 1/2 to three months depending upon the city/county requirements 
  • Construction time – approximately 9-10 months depending on scope and size of job